South Austin's newest trail is under construction. Will the Trump administration help pay for it?

An aerial view of the train tracks known as the Bergstrom Spur. On the left is Ben White Boulevard, a major highway. Elsewhere, low-rise warehouse type buildings and parking lots make up most of the scenery. In the middle of the image, train tracks are shown going straight off into the horizon.
Nathan Bernier
/
KUT News
The Bergstrom Spur, an abandoned railroad line that runs roughly parallel to Ben White Boulevard, will be converted to a 6.5-mile trail for cyclists and pedestrians. The biggest question now is who will pay for it.

Lee esta historia en español

An abandoned railroad line in South Austin is being converted into a trail for pedestrians and cyclists, with the first section set to open next year.

But uncertainty surrounding the Trump administration's freeze on federal grants has cast doubt on how much of the bill the feds will cover and whether the city will have to shift money away from other planned trails.

Construction kicked off after the holidays on the project known as the Bergstrom Spur Trail, a 6.5-mile pathway stretching from near St. David's South Austin Medical Center almost to Austin-Bergstrom International Airport.

A map showing the Bergstrom Spur Trail running from Vinson Drive to U.S. 183.
City of Austin
The 6.5-mile Bergstrom Spur Trail will be built in phases. The map shows the trail running to U.S. 183, but it will end a little short at Riverside Drive at U.S. 183.

The city secured $4.1 million in federal funding for the first phase of construction, thanks to earmarks from Congressman Lloyd Doggett, D-Austin. Congressman Greg Casar, D-Austin, secured $500,000 for the central portion of the trail.

Last week, Austin submitted a new federal grant application, hoping to secure millions more to complete the project. The estimated construction costs span from $12 million to $18 million.

If the request is denied, the project would still move forward, but at the cost of other trails in the pipeline.

A cross-section of the Bergstrom Spur Trail, showing a drainage ditch called an "Open Swale" followed by a 12-foot-wide bicycle path, a 2-foot-wide buffer, and an 8-foot-wide pedestrian path followed by another open swale.
City of Austin
The Bergstrom Spur would mostly be a 12-foot-wide bikeway and 8-foot-wide pedestrian path with a 2-foot buffer between. Some areas would have a 12-foot-wide path to be shared between people on bike and on foot with a 5-foot buffer between the trail and the road.

The Bergstrom Spur railroad line was built in the early 1940s to supply the Air Force base that would eventually become Austin-Bergstrom International Airport in 1999. The tracks have sat unused since 1993, but city officials have long seen the east-west corridor as a prime candidate for alternative transportation.

"This is the top of the city's urban trails priority list," said John Eastman, who oversees sidewalks and urban trails at Austin's Transportation and Public Works Department.

"This provides a really great set of connectivity into areas that really are historically underserved in terms of access to transit, access to trails and greenways," he said. "If you look through this kind of southeast corridor just south of 71, there's just not a lot of good connectivity in an east-west direction."

An aerial view of the abandoned train tracks next to Saint Elmo Elementary School.
Nathan Bernier
/
KUT News
The trail travels past Saint Elmo Elementary School on the right. This area is part of the first section, between Vinson Drive and South Congress Avenue, slated to be completed in 2026.

The deserted railroad line crosses major roads including South First Street, South Congress Avenue and the I-35 frontage roads, cutting through residential neighborhoods, behind strip malls and light industrial areas that are home to a growing number of breweries and distilleries. More than 40 bus stops are within a half mile of the tracks, including the South Congress Transit Center.

"We have been collaborating to make sure that all the connections work and that we understand where the trail is going to be so that we can make sure our bus stops are in the right place," Capital Metro CEO Dottie Watkins told KUT News.

The first section of the trail, a 1.12-mile stretch from Vinson Drive to South Congress, is fully funded, with the federal government covering 80% of the cost and the city paying the remaining 20%.

"I've requested money about three or four times, and we finally got the dollars in hand to encourage the city to move forward on the project," Doggett said.

A map showing the first segment of the Bergstrom Spur Trail to be constructed between Vinson Drive and South Congress Avenue.
City of Austin
This 1.12-mile western section of the trail is scheduled to be completed sometime in mid-2026.

But the remaining miles of the trail still lack secured funding. Austin officials submitted a new grant application last week for a BUILD Grant from the U.S. Department of Transportation, asking for up to $20 million to complete the trail and give a boost to CapMetro's public transit infrastructure.

A previous grant application in 2022 was rejected, but Eastman said federal officials indicated the proposal had been close to winning. City officials refined and resubmitted the request.

Adding to the uncertainty is President Trump's executive order freezing federal grants, a sweeping move that triggered multiple lawsuits. While courts have blocked the freeze for now, long-term funding approvals remain uncertain as agencies scramble to align with Trump's new spending priorities.

If Austin's latest grant application is denied, the city would have to pay for the remainder itself, which could delay other planned trail projects.

"We have sufficient funds available out of the bond," Eastman said, referring to $80 million for urban trails included in a $460 million bond approved by voters in 2020. "But it would put some other trail projects potentially on the back burner."

Austin officials are looking for indications about which grant programs could be permanently affected under the new administration.

"Day-by-day we're kind of trying to watch the federal government," said Council Member Paige Ellis, who chairs a panel of council members focused on transportation issues. "But we know that people support their dollars being used wisely and we want to make sure that we're advocating for Texas dollars to be spent in Texas."

Regardless of where the money comes, the head of the city's Transportation and Public Works Department, Richard Mendoza, told KUT News the Bergstrom Spur Trail is on track for completion in 2027.

Nathan Bernier is the transportation reporter at KUT. He covers the big projects that are reshaping how we get around Austin, like the I-35 overhaul, the airport's rapid growth and the multibillion-dollar transit expansion Project Connect. He also focuses on the daily changes that affect how we walk, bike and drive around the city. Got a tip? Email him at nbernier@kut.org. Follow him on X @KUTnathan.