Behind those walls along I-35, TxDOT is building one of the largest tunnels Austin's ever seen

Noise barriers surround construction on a tunnel drop shaft off of Cesar Chavez Street for the I-35 drainage tunnel on Tuesday, Aug. 26, 2025, in Austin.
Michael Minasi
/
KUT News
Noise barriers surround a construction site where a drop shaft is being drilled off of Cesar Chavez Street. The deep holes will provide access to a massive underground drainage tunnel required for TxDOT to sink the mainlanes up to 65 feet below ground level.

If you've been driving on I-35 through Central Austin, you may have noticed tall construction walls going up at certain points along the highway and wondered what's going on behind them.

Those barriers are designed to block the sound of machines digging deep holes called drop shafts for one of the largest tunnel projects in Austin history.

The tunnel is so large that building it will cause the ground to vibrate along its 6.5-mile path down I-35 and East Cesar Chavez Street, creating uncertainty about the risks to nearby structures.

One of the drop shafts being dug for the I-35 drainage tunnel.
/
Texas Department of Transportation
This is one of nine drop shafts being drilled for the I-35 tunnel project.

The drainage tunnel is required to prevent I-35 from becoming a raging river during rush hour rains. As part of a major expansion of the highway through Travis County, the Texas Department of Transportation is dropping the main lanes up to 60 feet below ground level from Holly Street to Airport Boulevard.

Those sunken main lanes, parts of which could be covered with giant decks by the city of Austin, will allow a clear view across the highway for the first time since it opened in 1962.

A rendering of I-35 at Holly Street looking north showing sunken lanes
Texas Department of Transportation
TxDOT plans to sink the main lanes of I-35 from Holly Street to Airport Boulevard. This is a rendering of the view from Holly Street looking north.

The lowered lanes will also serve as troughs for Austin's notoriously drenching rains when the sky opens up. So the 22-foot-wide tunnel will send that stormwater streaming to the Colorado River downstream of Lady Bird Lake.

In spring 2026, the first of two "double shield" tunnel boring machines will be delivered from Germany. The manufacturer Herrenknecht will send the underground factories in pieces to be assembled on site in Austin.

Like giant robotic earthworms, the German machines will bore the tunnel while simultaneously building its walls with panels of pre-cast concrete. The speed of the machines varies, but they're expected to be able to move up to 50 feet a day.

One machine will start near I-35 at Airport Boulevard and drill south. Another will tunnel west under Cesar Chavez Street from near U.S. 183. The machines, working at a depth of up to 200 feet, will meet near Cesar Chavez and I-35.

A view of I-35 from atop the Waterline tower, Austin's tallest building.
Lorianne Willett
/
KUT News
A view of I-35 from atop the Waterline tower, Austin's tallest building.

Besides the environmental concerns around such a large drainage project — like the air and noise pollution from trucks hauling excavated rocks and dirt 24/7, or routing the waters of Boggy Creek west of I-35 into the drainage tunnel, or pumping thousands of gallons of treated highway runoff into the Colorado River — the construction itself will rattle a lot more than nerves.

An overhead illustration showing the location of a pump station at the end of the 6.5-mile tunnel. The drawing of the pump, superimposed on a Google Earth satellite image, shows the facility within the interchange of U.S. 183 and ramp to Levander Loop with a pipe leading to the Colorado River.
Texas Department of Transportation
At the end of the 6.5-mile drainage tunnel, TxDOT is building a pump station at U.S. 183 capable of moving 130,000 gallons of stormwater per minute into the Colorado River. This slide is taken from a January 2024 workshop with possible contractors. TxDOT says the highway runoff will be filtered through screens to remove trash and some sediment. The state and city are designing a water quality pond to treat the runoff, but building it still requires city council approval.

"I think it's important to let folks know that outside the right-of-way, they'll probably feel vibrations," said Scott Ford, an environmental supervisor with TxDOT's Austin District.

A map depicting the I-35 drainage tunnel and pump station. The map shows a new drainage tunnel running along I-35 from Airport Boulevard to Holly Street and then east along Cesar Chavez Street to a pump station near US 183. Various drop shafts are marked along the route, including at Airport Boulevard, the Hancock Center, Edgewood Avenue, 15th Street, 11th Street, River Street, Brushy Street and Cesar Chavez Street.
Texas Department of Transportation
Nine drop shafts will be dug in all. Excavations are already underway along I-35 at Airport Boulevard, 11th Street and Cesar Chavez. Three more sites are being prepared at Brushy Street, River Street and 15th Street.

"The question then becomes, is that feeling going to cause a problem to their structure," Ford said. "You can feel the vibration and it not get close to doing any sort of structural damage."

Historic properties along East Cesar Chavez Street may wind up shaking. Almost 100 of them were constructed before 1930, according to a technical memo by TxDOT. Fourteen of those buildings are more than one story tall and "may need special attention during the construction phase," the memo warned.

The company building the tunnel, SAK and Shea, is supposed to survey the condition of all historic buildings along the tunnel's path before and after construction, watching for signs of damage. An agreement signed by TxDOT and the Texas Historical Commission requires close monitoring of vibration and quick adjustments if the ground is rattling too much.

https://www.youtube.com/watch?v=XQ6lz4rcSFA

To better understand what the vibrations might mean for these structures, KUT News asked a leading expert on how underground excavation affects buildings to review some of the project's technical documents. Those documents included a geotechnical baseline report and boring logs of the soil beneath Cesar Chavez.

"People will feel vibration in the same way if there was a big truck running down the road, they might feel it," said Debra Laefer, a civil engineering professor at New York University. "But what we know is it actually takes quite a bit of dynamic action for buildings to move and for them to be damaged. So while it might feel like a lot's going on, the building is probably absorbing it without difficulty."

Still, Laefer said, without conducting a site visit to Austin and inspecting individual properties, it's difficult for her to say anything with certainty. She suggested anyone living nearby prepare to document potential damage to their property.

A bigger risk from vibrations can come from how the soil settles after boring, Laefer said. The slow movement of ground around a tunnel could cause issues ranging from cosmetic problems like hairline cracks in walls to structural damage.

Lighter buildings such as single-family houses tend to put less pressure on the soil, while heavier buildings or large industrial facilities are "almost driving themselves towards the excavation or the tunnel movement," she said.

But Laefer said the geotechnical data she reviewed indicates the ground is "competent," meaning it's dense and well-compacted.

"If you imagine a bag of marbles and everything's kind of tight up against each other, there's less chance for movement," she said. "Whereas if the marbles are kind of moving around, any disruption to that, quite a few things are going to move."

The tunnel's pre-cast concrete liner should also help reduce the risk of soil shifting, she said.

"These would be things that would make me less concerned," Laefer said.

TxDOT says anyone with concerns can reach out to them by leaving a voicemail at (512) 366-3229 or by emailing CapExCentral@txdot.gov.

Before tunneling starts, the public will have a chance to see the machines up close. TxDOT's contract requires SAK and Shea hold two "Touch a Truck" events on Saturdays allowing the public to visit the site, touch the equipment and have any questions answered by experts. Those events are not yet scheduled.

Nathan Bernier is the transportation reporter at KUT. He covers the big projects that are reshaping how we get around Austin, like the I-35 overhaul, the airport's rapid growth and the multibillion-dollar transit expansion Project Connect. He also focuses on the daily changes that affect how we walk, bike and drive around the city. Got a tip? Email him at nbernier@kut.org. Follow him on X @KUTnathan.